German gas transmission operator Gascade has started permitting a 115km hydrogen pipeline that could connect the Port of Rostock to the country’s 9,000km hydrogen core network.
The Hyrow project, which is expected to begin operations in late 2028, is Gascade’s first new-build project within the national hydrogen network to advance from planning to formal approval processes.
The pipeline will run from Rostock to Wrangelsburg in Mecklenburg-Western Pomerania, connecting with the firm’s already completed 400km conversion of natural gas pipelines running from Lubmin to Bobbau in Saxony-Anhalt.
Preliminary archaeological investigations are expected to begin at 50 locations along the Hyrow route before the end of 2026, continuing into 2027 ahead of the targeted commissioning.
It follows an August 2026 capacity reservation agreement between Gascade and Rostock EnergyPort Cooperation, covering the injection of around two tonnes of green hydrogen per hour into the core network via Hyrow.
Equivalent to 48 tonnes per day, the reserved capacity could provide a route to market for future hydrogen production and imports at Rostock.
Alongside Hyrow, Gascade is advancing other new-build connections under its Flow programme, including the 120km Hybor pipeline in eastern Germany and the 15km Hylu connection to Ludwigshafen.
It comes as German transmission system operators (TSOs) continue the build-out of the ambitious core network.
In August, TSOs said almost 6GW of capacity had been reserved on a “paid basis,” doubling from figures reported in May.