Questionable data center forecasts are driving up Ohio…

Questionable data center forecasts are driving up Ohio…


Analysts have criticized PJM in general and Ohio in particular for making it difficult to build inexpensive solar, wind, and battery projects in recent years — all of which could have helped cushion rising costs now and alleviate projected capacity problems in the future.

Projections by utilities and the grid operator also drive plans for expanded infrastructure, because utilities map out those investments today on the basis of what they expect customers will need in the future.

If these data centers don’t show up …, you’re going to pay the costs,” said John Seryak, CEO and founder of the energy consulting firm RunnerStone.

In Ohio, both manufacturing and consumer advocates worry that plans to build transmission and other infrastructure are not being met with enough scrutiny.

Although large-scale projects are overseen by the Federal Energy Regulatory Commission, lower-level supplemental” transmission is up to the states, PJM’s Haque said. Those projects are necessary to meet growing demand, including that from data centers, especially where developers won’t bring their own power or nonetheless want to tie into the grid for backup.

Supplemental transmission projects can add up to billions of dollars, though. And in Ohio, no one is independently examining their prudence or cost-effectiveness, Maureen Willis, agency director for the Office of the Ohio Consumers’ Counsel, said at the OMA conference.

A 2025 Ohio law calls for utilities and state regulators to consider grid-enhancing technologies as a more cost-effective alternative to building traditional transmission projects. But it’s unclear how that provision and cost recovery will work together. A new rule limiting the time to question company witnesses about customer charges will make it even harder to challenge costs.

The Ohio Consumers’ Counsel filed a complaint with FERC in 2023, asking it to require scrutiny of the costs for supplemental transmission, but the agency has not yet acted. Last month the agency asked the commission to speed up its review.

OCC’s consumer-protection complaint has been collecting dust at FERC for nearly three years while billions more in transmission projects continue to be added,” Willis said. Consumers deserve answers, accountability, and protection from unjustified costs.”

In Ohio, the largest projected overall growth in demand is the tripling expected by AEP Ohio, Koomey said at the OMA event.

As of February, that AEP Ohio load forecast reflected signed contracts for 17.8 gigawatts of data-center demand planned to come online at various points through 2035, down from its earlier estimate in 2025.

Still, even at the lower level, critics question the figure. A March 2026 regulatory staff filing at the Public Utilities Commission of Ohio noted some double-counting for AEP Ohio’s expected data center growth.

At the PJM level, the grid operator released new guidance in January that alters its process for load forecasting and adds steps for states to review adjustments for large loads. Critics say that’s not enough.

Show us the demand. Show us what is being built. Show us who is paying for it. And show us what happens if the forecast is wrong,” said Belden of the Ohio Manufacturers’ Association Energy Group. Those are the questions any responsible business would ask before making a major investment. We should expect the same discipline when billions of dollars in grid investment are on the table.”

New investment should strengthen Ohio’s economy, not turn existing customers into an insurance policy for projects that may never materialize,” he said. 



Source link

Compare listings

Compare