Iberdrola supplies 170 GWh a year of renewable electricity from its Spanish wind and solar farms under a power purchase agreement [1]. That is less than the 200 GWh a year set when the companies took the final investment decision in September 2024, pv magazine reported [2]. The electrolysers are five 5 MW proton exchange membrane (PEM) modules from Plug Power [2].
The green hydrogen replaces part of the grey hydrogen, made from natural gas, used in the refinery’s processes, and is expected to avoid about 23,000 tonnes of CO2 emissions a year [1]. The project received €15 million from incentive programmes managed by Spain’s energy agency IDAE and funded by the EU’s NextGenerationEU recovery funds; around 25 Spanish companies supplied equipment or helped build it [1]. Total investment was more than €70 million at the final investment decision, according to pv magazine, which said the site is the first phase and is designed to allow more electrolysis capacity later [2].
“Our European refineries play an important role in energy security,” said Brenda Stout, BP’s senior vice president for refining, terminals and pipelines [1]. Mario Ruiz-Tagle, chief executive of Iberdrola España, said the project “shows how innovation and electrification with renewable energy” can improve industrial competitiveness [1]. When the investment decision was taken in 2024, operation was planned for the second half of 2026, pv magazine reported [2].