BP has started up its 25MW green hydrogen project, developed with and powered by energy firm Iberdrola, to begin replacing grey hydrogen at its refinery in Castellón, Spain.
With capacity to produce around 2,800 tonnes of green hydrogen per year, the plant will partially displace grey hydrogen already used at the site.
Previously targeting a May start-up, and once planned for a 200MW capacity, the plant uses a PEM electrolyser from Plug Power and received €15m ($16.4m) in NextGeneration EU Funding – just over 20% of its €70m ($76.7m) total cost.
It was developed under the pair’s 50/50 joint venture, Castellón Green Hydrogen SL (CHG).
BP is now also considering expanding capacity for refinery decarbonisation in the region, as well as targeting industrial markets, via its Castellón Green Hydrogen Phase 2 SL venture which secured €66.3m ($72.7m) in regional government funding in September.
Refining continues to emerge as one of the earliest and most significant markets for green hydrogen, with projects increasingly developed on, or adjacent to, existing industrial sites.
Spanish energy major Repsol recently took a €400m ($439m) final investment decision on a 150MW green hydrogen plant in Tarragona to replace grey hydrogen at its nearby refinery.
Its Spain electrolyser pipeline also includes 100MW plants for supplying refinery operations in Bilbao and Cartagena.