Charbone logs CAD $1.2m in sales amid gas production buildout

Charbone logs CAD .2m in sales amid gas production buildout


Canadian industrial gas firm Charbone has logged CAD $1.2m ($0.84m) in sales for the nine months ended 30 September 2026, as it advances plans to build out gas production assets.

In Q3 2026, gas income across Charbone’s Sorel-Tracy green hydrogen plant in Quebec and regional supply hubs for all industrial gases increased 21% to CAD $0.55m ($0.39m) from CAD $0.46m ($0.32m) in Q2 2026.

Operations began at the Sorel-Tracy plant in December 2025. The firm is currently building hydrogen capacity at the site through its Phase 1B production expansion, which was initially targeted for autumn 2026.

Benoit Veilleux, Chief Financial Officer and Corporate Secretary of Charbone, said, “[It] will take a few weeks more following an opportunity…[to integrate] other equipment to reach even higher purity level specifications and to recuperate vented UHP oxygen.”

The firm’s property, plant and equipment assets increased by CAD $5.5m ($3.87m) between 31 December 2025 and 30 September 2026, reflecting ongoing investment in the Phase 1B buildout and distribution infrastructure.

The firm recently added hydrogen and helium cylinder filling capacity at its Sorel-Tracy plant in line with plans to expand the facility into a multi-gas distribution hub.

Charbone announced its move beyond green hydrogen and expansion into industrial gas production and distribution in April of this year.

Under the new strategy, the firm signed a three-year ultra-high purity (UHP) oxygen supply contract in the US in the same month.